5 Eastwood Road Leppington NSW 2179
- Description
- Construction and operation of a medium voltage Battery Energy Storage System (BESS) (up to 5MW / 11MWh) comprising four battery modules/containers and associated electrical infrastructure, including an 11kV underground connection to the adjoining Endeavour Energy substation, noise walls, internal access road, stormwater works, earthworks, security fencing, the removal of 25 trees, landscaping and associated site infrastructure.
- Planning Authority
-
Camden Council
View source
- Reference number
-
2026/90/1This was created by Camden Council to identify this application. You will need this if you talk directly with them or use their website.
-
Date sourced
- We found this application on the planning authority's website on , 16 days ago. It was received by them earlier.
-
Notified
- 133 people were notified of this application via Planning Alerts email alerts
-
Comments